The customer asks your project to be completed 6 months earlier than planned.You think thi

  • 发布时间:
  • 浏览:96
  • 来源:大数据
The customer asks your project to be completed 6 months earlier than planned.You think this target can be reached by-overlapping project activities. This approach is known as (). A.balance engineering B.fast-tracking C.leveling D.crashing 请帮忙给出正确答案和分析,谢谢!
答案

验证码: 验证码:  

答案: 输入验证码查询

解析