In project management , a (1) is a listing of a project’s milestones, activities, and deliverables, usually with intended start and finish dates. Those items are often estimated in terms of resource (2) ,budget and duration, linked by dependencies and scheduled events. A.schedule B.activity C.plan D.contractor@@@SXB@@@A.finding B.balance C.allocation D.distribution 请帮忙给出正确答案和分析,谢谢!