【题目描述】 Management tells a project manager to subcontract part of the project to a company that management has worked with many times . Under these circumstances, the project manager should be MOST concerned about:A.making sure the company has the qualifications to complete the project . B.meeting management expectations of time . C.the cost of the subcontracted work . D.the contract terms and conditions . 【我提交的答案】: B【参考答案与解析】: