请教:PMP项目管理师考试(英文版)模拟试题及答案解析(1)第1大题第8小题如何解答?

  • 发布时间:
  • 浏览:42
  • 来源:大数据
【题目描述】 Management tells a project manager to subcontract part of the project to a company that management has worked with many times . Under these circumstances, the project manager should be MOST concerned about:A.making sure the company has the qualifications to complete the project . B.meeting management expectations of time . C.the cost of the subcontracted work . D.the contract terms and conditions . 【我提交的答案】: B【参考答案与解析】:
答案

验证码: 验证码:  

答案: 输入验证码查询

解析